Thursday, 27 May 2010

Singin In The Rain!

Rain at last! Following a period of 50 days with virtually no rain and some daytime temperatures in excess of 80 degrees the heavens finally opened yesterday with almost an inch of the wet stuff falling in the space of 12 hours. With more rain forecast for the weekend it looks like the difficult recent weather is finally changing.
The few parts of the course that the irrigation system does not cover and all the areas turfed in the winter were in dire need of a drink not to mention the restored dune areas where the trees were removed and the section on the seventh hole where the gorse was cut back.
Hand watering was consuming far too much of our time, especially at this critical time of the year from a greenkeeping perspective. The course has had to endure one of the harshest winters in recent memory, the last thing we needed was a slow spring coupled with the freakish drought.
This week and next are two of the most important in our golfing calendar with the Island Amateur Championships this weekend being followed by the European Seniors Tour next week. Tomorrow I will write a post on the preparations for these two events.

Tuesday, 11 May 2010

Top Dressing Greens

Today we spent the morning top dressing greens. This task is carried out routinely to help smooth the putting surface and to promote healthy turf. On this occasion we applied 20 tonnes of material to the greens using our spinning disc top dresser.

This was followed by a pass with a rubber dragmat to work the material into the base of the sward. Prior to top dressing we brushed the greens with rotating brushes to lightly remove organic matter and also cut the greens at 4.5mm.

The brushes used on the greens today

Monday, 10 May 2010

Still Dry

A grand total of 1.5mm or 0.059 of an inch of rain has fallen on the golf course since the first week in April. In the past week evapotranspiration levels have been in excess of 4mm per day leaving us with a large deficit which we fill with irrigation water.

 A screen shot of the weather station data. Note the two right hand columns for rainfall and ET. Click image to expand.
Just over 450000 litres of irrigation water was applied last night alone to try to replace the lost moisture. Of course there are areas on the course not covered by the irrigation system, these include some tee banks, walkways and roughs. These areas are suffering badly having not had proper growing conditions since spring 2009. Course staff are working hard to hand water areas which were turfed in the winter and also parts of the course which were seeded in the early spring but it is proving very difficult to keep up. The marram plugs on the 11th hole are struggling due to the weather conditions also. Again, hand watering is taking place but rain is desperately needed.

Monday, 26 April 2010

Chipping Area Update

We plan to open the chipping area on Saturday 1st May following the redesign work carried out over the winter. The turf has taken well and surfaces have been worked on as much as possible given the recent weather conditions. From now on the main green will be maintained in exactly the same way as the greens on the course so in time it will be of the same standard. Only short chip shots should be played to the main green.

 Mowing The New Green

A teeing area has been built to allow longer shots to be played to a landing area about 65m away. All shots from this area should be played from  the area defined by ropes.

 The New Teeing Area


The new bunker practice area has a dedicated landing area. Players should ensure they play towards the dedicated area only.

 New Bunkering With Landing Area Beyond

No Rain + Easterly Winds = Poor Growth

Jersey is officially in a period of drought. It is now 19 days since any rain has fallen on the golf course and our monthly running total currently stands at a shockingly low 9mm. The near constant easterly winds that we are experiencing have meant that the turf is extremely dry and grass growth is almost non existent. Although our irrigation system is fully operational, the persistent cool air and soil temperatures are preventing us from apply much water. A soil temperature of around 10C is required to enable good growing turf. Cold water landing on already cool soils only serves to further lower soil temperatures lessening the chance of any growth taking place. Irrigation is taking place during the warmest days but it is impossible to apply enough water without cooling the soil too much.
Evapotranspiration (ET) is a term used to describe the sum of evaporation of moisture and plant transpiration from the ground to the atmosphere. Evaporation accounts for the movement of water from the ground to the air while transpiration accounts for the loss of water from within the plant itself. We are currently seeing an ET rate of around 3mm per day, just over 70mm for the month so far. The 9mm of rainfall that has fallen and 26mm of irrigation that has been applied in the same period has left a large deficit.
We use wetting agents on the greens which help the soil particles hold onto available moisture for an extended period, because of this the moisture level in our greens is being maintained at an acceptable level despite the difficult conditions. We do not have enough moisture to promote strong growth but there is enough to at least ensure survival in this testing time. Of course ideally, at this time of year, we would like a more typical spring weather pattern with sunshine and regular showers. A cycle of sunshine and showers is ideal to promote grass growth and allow recovery from the harsh winter months we have experienced. Current conditions means that any fertilizer applications are compromised and frequent top dressing is impossible. Mechanical operations carried out to refine the turf texture and smooth the surface have been postponed until stronger grass growth comes. All this leaves playing surfaces in a less than perfect state for golf and makes the job of a greenkeeper a very difficult one. We can't fight mother nature, we must simply wait until conditions improve enough to allow us to work effectively on the surfaces once again.

Wednesday, 31 March 2010

Maintenance Week Update



Despite the high winds and rain work on the greens this week has progressed well. All surfaces have been scarified using the pedestrian machine pictured above. Due to the need to work in dry conditions, much of the work was carried out between the many rain showers we have had in the last three days. Half the team worked late in dry conditions yesterday afternoon to ensure the work could be completed.

Overseeding

Overseeding work has been completed on 18 of the 20 greens. Only the 11th and the Western putting green remain. Two passes of the seeder were carried out on holes 4 and 6 to improve sward density following the application of herbicide last autumn. All seeded greens have been top dressed and ironed to reinstate levels and smooth out the surface.

Saturday, 27 March 2010

Spring Maintenance Week

Our spring maintenance week starts from Monday 29th March. We plan to carry out a number of tasks which I will explain in this post.
Greens will be scarified in two directions to remove some organic matter from the base of the turf. A pedestrian scarifier will be used and the arisings will be collected. This process will not disrupt the short term playing quality of the greens. Dry conditions are required for this task to be carried out effectively.
Following the scarification we will overseed the greens. Our disc seeder will be used to introduce a browntop bentgrass mix of seed into the greens. The new grass will help fill out the sward, improving density to achieve a smooth as surface as possible. Greens 4 and 6 will particularly benefit from this process following the chemical treatment carried out in those areas last year. Again, dry conditions are required for this task to be carried out properly.
Finally greens will be top-dressed. We aim to apply around 20 tonnes of material to the putting surfaces. Dry weather is again required for this task to be carried out properly so fingers crossed for a sunny few days next week. To allow work to be carried out in good time, one tee starts will be in place and greens will be removed from play while work is in progress. Disruption to play will be kept to a minimum but I hope all players will understand the importance of completing the prescribed work in a timely manner.

Tuesday, 9 March 2010

Hole 7 Gorse Management

During the recent cold weather we have taken the opportunity to address the problem of old, degenerate gorse on the 7th hole.

  Before Work Commenced

It is very sad to see this beautiful golf hole covered in extremely degenerate gorse and unsightly bracken and bramble. From the tee banks, over the carry to the fairway and at either side of the path near the approach to the green the rough areas are suffering terribly from years of neglect. In accordance with our Ecological Management Plan, we have set out to reinstate the rough grasslands by removing the dead and dying material. Some of the gorse will be retained but to encourage healthy and robust plants it is being coppiced to a height of 150mm above ground level. Whilst this seems extreme, it is amazing how quickly the gorse will regenerate. 


The ultimate aim for these areas is to achieve a balance between rough grasses and small pockets of gorse. Once the brash has been removed some light seeding work will take place. Bracken and bramble regrowth will be chemically treated as the need arises.

Wednesday, 3 March 2010

Chipping Area Redesign

The chipping area behind the 1st green has been in need of refurbishment for some considerable time. With bunkers that are too deep, greens of poor quality and a generally uninspiring layout it was decided to try to make significant improvements to the area.

Just before work started 

Following a period of consultation to agree the new design, it was established that we needed to make more use of the limited space available. Long pitch shots and an array of short chip shots needed to be accommodated along with bunker practice .
We lifted the turf from the existing greens first and layed it out at the turf nursery area in the valley. Next we constructed the landing area for pitch shots. This area is around 350m2 in size and will allow shots to be hit from the practice tee around 65m away.

 The new landing area

We then began the construction of the teeing area. The area was cleared before stakes were put in to establish levels. A sand sub base was brought in then 100mm of rootzone was added to the top.

 Top soil is brought in to the correct levels

Irrigation pipes and heads were positioned next.
























The 250m2 tee was then turfed using sods from the centre of the chipping area. When open, play from this area will be restricted to marked sections between ropes so as to control wear.



We then cleared the rest of the turf from the new green site and rotovated the soil. An excavator was hired to shape the new green and green surround.
 Initial shaping of the new green begins

 For the green we tried to ensure there was enough flat areas to have around 5 pins at any one time. On the surround we created hollows, swales and banks so a large variety of chip shots can be practiced.
 








Once we were happy with the shape we used mechanical and manual means to firm and rake out the ground ready for turf.

 



With the final raking completed we were able to begin turfing the 550m2 green. 

Two new bunkers are currently being constructed on the south side of the practice area. These will play to a dedicated green away from the pitching and chipping areas. This will allow more people to safely use the facility at the same time.

Tuesday, 2 March 2010

Course Update

My apologies for the length of time since the last blog post.

Lots of work has been done on the course in the last two months of which I will give a brief outline of in this post. A number of more detailed posts will follow soon which deal with individual projects we have been undertaking.

The course has fared quite well recently despite the testing weather conditions we have been experiencing. Surfaces have remained reasonably firm and dry for the time of year which has been great for golf. All putting surfaces were verti-drained in February to ensure we continue to have good movement of air and moisture through the soil profile.  Although the holes from this operation are currently still visible, the effect on putting is minimal compared to the huge benefits this operation has to the on going health of the greens. The 38mm of rain which fell in the early hours of Sunday morning caused no problem to the greens, unfortunately the same cannot be said for some the clay fairways!
The winter programme has progressed well. All bunker refurbishments have been completed and are looking good. Sand will be added to all bunkers in the next fortnight so they are ready for the start of the season. Lots of work has been carried out on trees and gorse around the course as per the Ecological Plan and I will post more about this shortly.  To round things off for now, we have spent a lot of time rebuilding the chipping area recently. I will post a seperate blog entry on this topic tomorrow.